Sim-Ex™ Practice Exams for PMP Practice Questions

Home     Previous     Next

Q2. You have just been hired as a project manager in a development company and have been assigned to manage a project. You have realized that detail planning will be needed for project success and decided to apply project management knowledge in a preferred order to achieve the desired project performance. Which of the below choice you need to follow to assist the project plan development?

A. Organization's business need

B. Internal rate of return

C. Constraints optimization method

D. Governmental or industry standards

Correct Answer: D

Explanation:

Governmental or industry standards is an enterprise environmental factor that can influence the develop project management plan process.

Domain Name: 4. Integration
Reference: PMBOK5 Section 4.2 Page 90

Home     Previous     Next


Disclaimer: Simulationexams.com is not affiliated with any certification vendor, and Sim-Ex™ Practice Exams are written independently by SimulationExams.com and not affiliated or authorized by respective certification providers. Sim-Ex™ is a trade mark of SimulationExams.com or entity representing Simulationexams.com.PMP® is a trademark of PMI™.