Q1. Tim, the new project manager of US based developer company has very little project management experience, but he has been assigned as the project manager of a new skyscrapers project. Because he is working in a matrix organization to complete his project, he can expect communication to be:
A. Open and accurate
B. Hard to automate
C. Complex
D. Simple
Correct Answer: C
Explanation:
In a matrix organization, the communication is expected to be complex. Hard to automate in some cases right, but is not a general characteristic of matrix organization. So, Complex is the obvious choice. In Projectized organization it can be simple.
Domain Name: 1-3. Foundational
Reference: PMBOK5 Section 2.1 Page 21
Disclaimer: All Simulation Exams practice tests, study guides and/or material are neither sponsored by, nor endorsed by, nor affiliated with Program Management Institute (PMI)® or any other company. All trademarks are trademarks of their respective owners and duly acknowledged. PMP™ is registered trade marks of Program Management Institute (PMI)®. The practice tests material is a copyright of SimulationExams.com and the same is not approved or endorsed by respective certifying bodies. Thank-you for your interest in Simulation Exams. Please see read me file before you download, install, and/or use any software from SimulationExams.com For any information or questions regarding this Website, please e-mail webmaster at simulationexams.com