Sim-Ex™ Practice Exams for PMP Practice Questions

Home     Previous     Next

Q3. The Dolphin project for Singapore safari World Company to relocate dolphins to new area is finished last week. The project manager is now working on collecting and recoding project records. Why it is so important to collect project records at the end of the projects?

A. Support cost and time decisions

B. Documents the critical decisions made during the project

C. To recall what happened in the project

D. Create basis to issue experience letter for team members as well as PM

Correct Answer: C

Explanation:

Lessons learned documents describes more than just the critical decisions made. It helps to recall what went right, wrong, progress throughout the project. Support cost and time decisions and creating basis to issue experience letter for team members as well as PM are correct but not the most important reason to collect project records.

Domain Name: 4. Integration
Reference: PMBOK5 Section 4.6 Page 101

Home     Previous     Next


Disclaimer: Simulationexams.com is not affiliated with any certification vendor, and Sim-Ex™ Practice Exams are written independently by SimulationExams.com and not affiliated or authorized by respective certification providers. Sim-Ex™ is a trade mark of SimulationExams.com or entity representing Simulationexams.com.PMP® is a trademark of PMI™.