Q3. The Dolphin project for Singapore safari World Company to relocate dolphins to new area is finished last week. The project manager is now working on collecting and recoding project records. Why it is so important to collect project records at the end of the projects?

A. Support cost and time decisions

B. Documents the critical decisions made during the project

C. To recall what happened in the project

D.
Create basis to issue experience letter for team members as well as PM

  Correct Answer: C

 

Explanation:

Lessons learned documents describes more than just the critical decisions made. It helps to recall what went right, wrong, progress throughout the project. Support cost and time decisions and creating basis to issue experience letter for team members as well as PM are correct but not the most important reason to collect project records.

Domain Name: 4. Integration
Reference: PMBOK5 Section 4.6 Page 101

Home
       Previous      Next

Copyright © 2000-2017 SimulationExams.com All rights reserved

Website design by Anandsoft.com

Disclaimer: All Simulation Exams practice tests, study guides and/or material are neither sponsored by, nor endorsed by, nor affiliated with Program Management Institute (PMI)® or any other company. All trademarks are trademarks of their respective owners and duly  acknowledged. PMP is registered trade marks of Program Management Institute (PMI). The practice tests material is a copyright of SimulationExams.com and the same is not approved or endorsed by respective certifying bodies. Thank-you for your interest in Simulation Exams. Please see read me file before you download, install, and/or use any software from SimulationExams.com  For any information or questions regarding this Website, please e-mail webmaster at simulationexams.com