Q9. Joshua is a project manager of a matrix organization involved in a project to develop scheduling software for a financial organization. This project has many critical activities and requires experts from various functional departments within organization. But his project is not a very high-profile one. Hence, there is a chance that the functional managers won’t agree about his requirement. Which of the following techniques will he need to apply?

A. Negotiation

B. Recognition and Reward

C. Procurement

D. Authority

  Correct Answer: A

 

Explanation:

The correct response is Negotiation. Usually, it requires bargaining in order to reach an acceptable arrangement. The project manager has to negotiate with functional manager on different issues during the life cycle of project including acquiring project team.

Domain Name: 9. HR
Reference: PMBOK5 Section 9.2.Page 270

Home
          Previous    Next

Copyright © 2000-2017 SimulationExams.com All rights reserved

Website design by Anandsoft.com

Disclaimer: All Simulation Exams practice tests, study guides and/or material are neither sponsored by, nor endorsed by, nor affiliated with Program Management Institute (PMI)® or any other company. All trademarks are trademarks of their respective owners and duly  acknowledged. PMP is registered trade marks of Program Management Institute (PMI). The practice tests material is a copyright of SimulationExams.com and the same is not approved or endorsed by respective certifying bodies. Thank-you for your interest in Simulation Exams. Please see read me file before you download, install, and/or use any software from SimulationExams.com  For any information or questions regarding this Website, please e-mail webmaster at simulationexams.com