Q8. Perform quality assurance process uses data from quality measurements to track the way we work and improve it all the time. Which of the below statements is incorrect about quality assurance?

A. During project planning quality assurance measures how long it takes to plan the project or measure other areas of planning performance

B. The quality assurance process reviews the quality measurement plan and uses the measurements taken in the quality control process.

C. Quality audits are usually done by quality assurance department to look for new lesson learn and good practices that the project can contribute.

D. Perform quality assurance process provides a way for continuously process improvement of all the process

  Correct Answer: A

 

Explanation:

Quality assurance works at execution phase, not planning. Quality control measures how long it takes to plan the project or measure other areas of planning performance.

Domain Name: 8. Quality
Reference: PMBOK5 Section 8.2 Page 245

Home
         Previous      Next

Copyright © 2000-2017 SimulationExams.com All rights reserved

Website design by Anandsoft.com

Disclaimer: All Simulation Exams practice tests, study guides and/or material are neither sponsored by, nor endorsed by, nor affiliated with Program Management Institute (PMI)® or any other company. All trademarks are trademarks of their respective owners and duly  acknowledged. PMP is registered trade marks of Program Management Institute (PMI). The practice tests material is a copyright of SimulationExams.com and the same is not approved or endorsed by respective certifying bodies. Thank-you for your interest in Simulation Exams. Please see read me file before you download, install, and/or use any software from SimulationExams.com  For any information or questions regarding this Website, please e-mail webmaster at simulationexams.com