Q4. WBS process allows the team to walk through the project in their minds and thus improves project plan. Who is responsible for creating WBS for a project?

A. Must be done by Project manager

B. Created by one person in the team taking help of stakeholders

C. Sponsor

D. Functional manager with their respective concern

  Correct Answer: B

 

Explanation:

The WBS list is generally created by one person in the team taking help of stakeholders. The project manager can do that but he is not the appropriate person for this purpose.

Domain Name: 5. Scope
Reference: PMBOK5 Section 5.4 Page 126

Home
         Previous    Next

Copyright © 2000-2017 SimulationExams.com All rights reserved

Website design by Anandsoft.com

Disclaimer: All Simulation Exams practice tests, study guides and/or material are neither sponsored by, nor endorsed by, nor affiliated with Program Management Institute (PMI)® or any other company. All trademarks are trademarks of their respective owners and duly  acknowledged. PMP is registered trade marks of Program Management Institute (PMI). The practice tests material is a copyright of SimulationExams.com and the same is not approved or endorsed by respective certifying bodies. Thank-you for your interest in Simulation Exams. Please see read me file before you download, install, and/or use any software from SimulationExams.com  For any information or questions regarding this Website, please e-mail webmaster at simulationexams.com