Q1. Tim, the new project manager of US based developer company has very little project management experience, but he has been assigned as the project manager of a new skyscrapers project. Because he is working in a matrix organization to complete his project, he can expect communication to be:

A. Open and accurate

B. Hard to automate

C. Complex

D.
Simple

  Correct Answer: C

 

Explanation:

In a matrix organization, the communication is expected to be complex. Hard to automate in some cases right, but is not a general characteristic of matrix organization. So, Complex is the obvious choice. In Projectized organization it can be simple.

Domain Name: 1-3. Foundational
Reference: PMBOK5 Section 2.1 Page 21

Home
           Next

Copyright © 2000-2017 SimulationExams.com All rights reserved

Website design by Anandsoft.com

Disclaimer: All Simulation Exams practice tests, study guides and/or material are neither sponsored by, nor endorsed by, nor affiliated with Program Management Institute (PMI)® or any other company. All trademarks are trademarks of their respective owners and duly  acknowledged. PMP is registered trade marks of Program Management Institute (PMI). The practice tests material is a copyright of SimulationExams.com and the same is not approved or endorsed by respective certifying bodies. Thank-you for your interest in Simulation Exams. Please see read me file before you download, install, and/or use any software from SimulationExams.com  For any information or questions regarding this Website, please e-mail webmaster at simulationexams.com